Building a house in phases in Guyana: when half a house counts as finished

Illustration of a two-storey house in Guyana with one floor finished. Not the homeowner's house.

Introduction

Last verified: October 2026

Last week a homeowner who watches my channel wrote to me about her house. She told me to go ahead and share what she wrote, as long as I kept her name out of it. So no name.

She designed what she called “a modest two storey.” Three thousand square feet. Her next word was “Ouch!”

Both floors are concrete slab. The roof is on. Upstairs, the plumbing rough-in is in and the electrical rough-in is going in as we speak. Plaster is next. Then, in her words, life threw a curveball and “labour cost exploded.”

So she made the call I wish more people made earlier. She’s finishing one floor, three bedrooms and two baths, plus the fence, the bridge and some site work, so the house is livable. The other floor waits.

Then she asked me something I haven’t stopped thinking about. “Do you consider an upper floor on stilts a finished home? They are all over Guyana.”

The short answer

Yes, if it was planned. A floor you chose to leave for later, closed in and priced, is a finished phase of a house. A floor you ran out of money on is a stall, even when the two look the same from the road.

The difference is a decision made on paper. The cheapest time to make it is before a single block is laid. The next cheapest is now, before the plaster goes on.

What she wrote

Here’s the part of her message I asked to share, exactly as she sent it.

Too often what the bank approves (plus savings) is maxed out on the super structure with bare bones allocation for finishes and site works. Incomplete planning obliterates false contingencies. The variables that can be outside of the homeowners control also spring surprises. I fell in love with my custom design and broke ground before the education your channel provides was available. There have been tradeoffs made but I’ve been forced to become better at managing mid-build by default.

A homeowner building in Guyana

Read her first sentence again. I’ve been trying to say that for years, and she did it in one line. The approval plus the savings is one number. The structure eats it first, because the structure is what everybody can see. By the time anyone prices the kitchen, the money is in the walls.

What a 3,000 sq ft two-storey costs, and where the money goes

Here’s her size run through our published rates. These aren’t her figures. Her budget is her business.

Finish levelGYD per sq ft3,000 sq ft finished
Standard spec28,000 to 32,000GYD 84 to 96 million
Mid-range custom33,000 to 42,000GYD 99 to 126 million
High-end45,000 to 55,000+GYD 135 to 165 million and up

Now the part that catches people. On a 2,852 sq ft two-storey on the East Bank that we costed phase by phase, the roof went on at 29 percent of the money. Foundation, floors, walls and roof. Everything you can see from the road.

At standard spec on her size, that’s about GYD 24 to 28 million. The other 71 percent is finishing, GYD 60 to 68 million, and almost none of it shows from the road. The full phase-by-phase breakdown is in what it costs to finish an unfinished house.

So a house can look nearly done from the street and still have most of its money ahead of it.

Why finishing half a house costs more than half

This is where some of you will disagree with me. Building in phases does not cut the finishing bill in half.

The floor you finish first carries the expensive parts. The kitchen. At least one full bathroom. The electrical panel. The water tank and pump. The septic. On that East Bank house, the kitchen, bathrooms, closets, stairs and trim came to 15.8 percent of the whole build on their own, more than the foundation. Electrical was another 8.8 percent. Most of both lands on whichever floor you finish first.

The floor that waits is mostly bedrooms, walls, tile and paint. Cheaper to finish, and dearer every year you wait. On that same house the finishing work was costed at GYD 41.6 million. At today’s rate the same scope is GYD 57 to 65 million. Same rooms. Same tile.

When half a house is finished, and when it’s a stall

Back to her question. Guyana has built houses on stilts for generations. Upstairs is the home. Downstairs is the car and the hammock. Nobody calls those houses unfinished, because they were drawn that way.

A two-storey with a floor waiting is a different house, and here’s the test I use. The waiting floor is a finished phase when four things are true.

It’s closed in, so rain and strangers stay out. It’s safe, with rails on the stairs and on any open slab edge. Everything that passes through it to the floor you live on is done and tested. And its finishing has a written price and a target date.

Miss one of those and you have a stall. Stalls cost more after every rainy season.

By that test, if she gets those four right, she owns a finished house the day she moves in. Some people say a house is finished when the drawing is finished. I don’t. The drawing was a plan made before the prices moved. The house you can live in and keep paying for is the one that counts.

Before you plaster

She’s about to plaster, so this part is for her and for anyone at the same stage. Plaster is the line. After it goes on, every fix means breaking finished work.

  1. Test everything inside the walls of the floor you’re finishing. Pressure-test the water lines and leave the gauge on overnight. Have the electrician check every circuit before the plasterer shows up.
  2. Run what the waiting floor will need through the finished one now. Pipes, drains and conduit, capped and labelled. Chasing a plastered wall later costs more than the pipe.
  3. Size the panel, the water and the septic for the whole house, not the half you’re finishing. A panel with no room for the second floor’s circuits means a second panel later.
  4. If the waiting floor isn’t wired yet, run empty conduit and pull the wire when you finish it. Copper in an empty floor is the first thing to walk off a site.
  5. Close the waiting floor. Windows, or boarded openings at the least, and a door that locks. Water is what turns a waiting floor into a repair job.
  6. Make it safe. Rails on stairs and slab edges, and grilles anywhere someone can climb in.
  7. Write the waiting floor’s scope down and price it at today’s rates. Then hold back 10 percent of what you have left for the floor you’re finishing, because that’s where the surprises live.

If you’re building from abroad

Most people reading this live overseas. A waiting floor is harder to manage from there. Nobody walks through it after the first heavy rain. Nobody notices the window somebody pried open.

If you phase from abroad, pay someone you trust to walk the empty floor every month and send you photos. Put that visit in the budget like any other line.

The rule behind it

I build by what I call the Completion Doctrine. A house doesn’t start until it’s designed, costed to the last fixture, and the money to finish it exists in writing. Starting is easy. Finishing is rare.

Phasing fits inside that rule when the phase is the plan. If you know on day one that you can finish 1,500 square feet and not 3,000, design phase one as a complete home and phase two as an addition. That’s a different drawing. The kitchen sits where phase one needs it. The stairs go where they won’t cut through a finished room. The roof slab gets designed to carry the floor that’s coming.

You’ve seen the other version. Steel sticking out of a roof slab for a second floor that comes fifteen years later, or never. Designed for it, that steel is a plan. Left there because the money stopped, it’s rust.

She broke ground, in her words, “before the education” was out there. She’s making the right call anyway. She told me she loves the house she’s going to finish, “now that pragmatism has [taken] a comfortable seat right next to my dreams.”

Who this is for

If you’re planning a house in Guyana and you haven’t started, apply for a Build-Readiness Review. We take your budget, your land and the house you have in mind, and cost it before anyone draws a line, including whether it should be built in phases. If you go ahead and build with us, the fee comes off the build in full.

Already building and stuck between floors? Send photos of where you are on WhatsApp to +592 663 9613, with what’s left to do and what’s left in the bank. I read every one.

Not ready for either? Get the BackHome Building Guide.

US$1,500. Application required, and we decline more projects than we take.

Sources

Construction rates are BackHome Developments’ published 2026 rates. The 29 percent roof figure and the phase shares come from a documented BackHome estimate for a 2,852 sq ft standard-spec two-storey on the East Bank. The homeowner’s words are quoted with her permission, name withheld.

This is a planning guide, not a quotation. Every site and design prices differently.