Change orders: what one small change costs once your build has started

A finished bathroom

Introduction

Last verified: September 2026

Two clients ask for the same change: swap the wall shower for a rain head. Same fitting, same bathroom, same price for the part.

One pays the difference in price. The other pays for the fitting, a plumber’s second trip, pipes moved inside a finished wall, and a week of the schedule.

The only difference between them is when they asked.

The short answer

A change order costs the price difference, plus whatever has to be undone, redone and waited for. Made on paper before you sign, a change costs a redraw. Made after the pipes or wires are in, the same change costs the part, the tear-out, the trade’s return trip and the days lost. On our jobs, every change is priced in writing and signed by you before anyone touches it.

The shower head

I’ve used this example with clients since my Toronto days, because it shows the whole problem in one bathroom.

The first client decides on the rain head a week after signing. The plumber hasn’t been to site yet. We change the drawing, change the order, and the client pays the difference between the two fittings. Nobody loses a day.

The second client decides after the plumber has roughed in the bathroom. The pipes are in the wall, in the wrong place for a rain head. Now the plumber comes back, the wall gets opened, the pipes get moved, and the tiler waits until it’s done. The client pays for the fitting, the plumber’s time, the repair and the delay.

Same change. The price of it was set by the calendar.

What a change costs, stage by stage

When you make the changeWhat you pay for
On paper, before you signA redraw
After signing, before it’s orderedThe price difference
After it’s ordered, before it’s installedThe difference, plus the order you no longer want
After the rough-in: pipes, wires, openingsAll of the above, plus tear-out, the trade’s return and the lost days
After finishesAll of the above, plus breaking finished work and doing it twice

The part people most want to change is also the most expensive part of the house. On our documented standard-spec build, the kitchen, bathrooms, closets, stairs and trim together came to 15.8 percent of the total, more than the foundation. It’s also the last thing installed, which means by the time most people change their minds about it, everything around it is already built.

Why a delay costs more here

In Guyana a lost week isn’t always just a week.

The coast has two rainy seasons, the main one from mid-April to the end of July with its peak in June, and a second from late November into January. A change that holds up the walls in March can push the roof into June. The roof is the stage the rain stops cold, so two weeks of change can turn into six weeks of waiting on the weather.

And if the new tile or fitting isn’t in stock locally, the wait is however long the next order takes to arrive.

Where changes really come from

This is where people go wrong. Most changes aren’t new ideas. They’re decisions that were never made.

The tile nobody picked before the start. The kitchen layout that was “to be confirmed.” And the family member who visits the site, sees the walls going up, and has a thought about the window.

Decide one thing early: who can ask for a change. On our jobs, a change only happens once the client signs it. An uncle on site can ask a question. He can’t approve a window.

How we handle it

Every selection is made before construction starts, in your client portal, from wherever you live. If you still want a change after that, it’s priced in writing first. You see the price and the days it adds, and you sign it in the portal before anyone touches the work. Nothing extra is added to your house without your signature.

If you’re still changing your mind about the house, you’re not ready to start building it. I’d rather wait with you than start without you.

The rule behind it

I build by what I call the Completion Doctrine. A house doesn’t start until it’s designed and costed down to the last fixture, and the money to finish it exists in writing. Starting is easy. Finishing is rare.

Change orders are where that rule gets tested after the start. Scope is locked before the build, before a single block is laid, because every decision you make on paper is a decision you don’t pay for twice on site.

Frequently asked questions

What is a change order?

A written change to the agreed scope of your build, with its price and its effect on the schedule, signed before the work is done.

How much does a change order cost?

The price difference, plus anything that has to be removed, redone or waited for. The later the change, the more of those it includes.

Can I change my mind after construction starts?

Yes, but it’s priced in writing and signed by you first, and it costs more the further the build has gone.

Who this is for

If you’re planning a custom house and want every decision made on paper first, apply for a Build-Readiness Review. We take your budget, your land and the house you have in mind, and cost it before anyone draws a line. If you go ahead and build with us, the fee comes off the build in full.

Not ready yet? Get the BackHome Building Guide. It’s the ten pages I’d want you to read before you hire anyone.

US$1,500. Application required, and we decline more projects than we take.

Sources

The finishes percentage comes from a BackHome Developments estimate for a 2,852 sq ft standard-spec two-storey at Golden Grove, East Bank Demerara, with client details removed. Rainy season dates are from the Hydrometeorological Service of Guyana.

This is a planning guide, not a quotation.