Last verified: September 2026
A standard-spec two-storey house in Guyana costs GYD 28,000 to 32,000 per square foot to build, all trades included. On a 2,852 sq ft four-bedroom that’s roughly GYD 80 to 91 million, or USD 399,000 to 456,000. The drawings, the permit submission and the permit fees are all inside that figure, because we are a design and build firm. Land and yard works sit outside that.
Below is the full phase-by-phase breakdown from a real estimate on a real lot at Golden Grove, East Bank Demerara, priced in May 2026 against confirmed supplier quotes. It was one of our early projects and it carries early-project pricing, so the total sits under our current rate. I’m publishing it anyway, because what transfers from one build to another isn’t the total. It’s the proportions. And almost nothing you’ll find online shows you those.
If you already have a number in mind, run it before you read on. The Completion Check takes four questions and shows where your money stops.
If you’d rather watch, I go through these numbers here.
What “per square foot” includes, and what it leaves out
Every cost guide in Guyana quotes a per-square-foot rate. Very few of them tell you what’s inside it.
The figure above covers everything from the footings to the paint: foundation, floor structure, roof, walls, windows, doors, plumbing, electrical, air conditioning, floor finishes, painting, kitchen, bathrooms, closets, stairs, trim, water storage and septic. That’s a house you can move into.
What it does not cover is the land, yard sand fill, the driveway, the perimeter fence, a solar system, a standby generator, or VAT. On a fresh Golden Grove or Diamond lot, site works and land preparation will add several million before anyone digs a footing.
So when you see the number, ask what’s outside it. That’s usually where the gap between the budget and the finished house lives.
Why some cost guides say US$300 to $700 per square metre for Guyana
There’s a site currently ranking for Guyana construction costs that quotes US$300 to $700 per square metre. Run the arithmetic. A square metre is 10.76 square feet, so $300/m² works out to about US$28 per square foot, or GYD 5,574. The top of their range, $700/m², is about GYD 13,000 per square foot.
They then price a “standard 3-bedroom” of 150 m², which is 1,615 sq ft, at US$45,000 to $105,000.
That same 1,615 sq ft house at standard spec comes to GYD 45.2 million, about US$226,000. Their top end is less than half of it. Their bottom end is about a fifth.
I’d guess that page is generated from a template and populated per country without anyone pricing a single job here. If you budget off it you will run out of money somewhere around the electrical rough-in.
Where the money actually goes, phase by phase
This is the anonymised estimate. Standard-spec two-storey, 2,852 sq ft, four bedrooms, three ensuites plus a powder room, reinforced concrete with a timber-joist upper floor, prepainted zinc roof, Golden Grove East Bank. Supplier pricing confirmed with Gafoors, GuyanaFrame and Floor It Guyana. Exchange rate at 1 USD to 200 GYD. Builder margin is inside these figures.
Read the percentages, not the total. As set out below, this was an early project and the total reflects early pricing. The proportions are what hold.
| Phase | GYD | Share of build | Running total |
|---|---|---|---|
| Foundation and ground structure | 8,313,544 | 14.2% | 14.2% |
| Upper floor structure | 2,581,226 | 4.4% | 18.6% |
| Roof framing and prepainted zinc | 3,239,904 | 5.5% | 24.1% |
| Exterior walls | 2,918,136 | 5.0% | 29.1% |
| Interior partition walls | 3,934,368 | 6.7% | 35.8% |
| Windows (26 aluminum casement) | 1,260,557 | 2.1% | 37.9% |
| Doors (28) | 3,327,000 | 5.7% | 43.6% |
| Plumbing | 3,582,228 | 6.1% | 49.7% |
| Electrical | 5,165,100 | 8.8% | 58.5% |
| Air conditioning (9 zones) | 3,175,949 | 5.4% | 63.9% |
| Floor finishes | 4,284,960 | 7.3% | 71.2% |
| Painting, interior and exterior | 3,905,481 | 6.7% | 77.9% |
| Kitchen, bathrooms, closets, stairs, trim | 9,270,934 | 15.8% | 93.7% |
| Water storage and pressure system | 1,917,920 | 3.3% | 97.0% |
| Septic and wastewater | 1,800,000 | 3.1% | 100% |
| Total | 58,677,307 GYD | 20,574/sq ft |
Add the 10 percent contingency we recommend and it’s GYD 64,545,038, about GYD 22,632 per square foot.
Roof on is 29 percent of the money
Look at the running total column again. Foundation, floor structure, roof and exterior walls together come to GYD 17,052,810. That’s 29 percent of the build.
The house at that stage is the one people photograph. Block up, roof on, looks like something. Family drives past on a Sunday and tells you it’s nearly done.
It’s spent under a third of the budget.
If you already own one of these, we have costed what it costs to finish a stalled house separately. This is why houses stall in Guyana, and it has almost nothing to do with contractors running off with money. A man budgets 40 million (see what GYD $40 million actually builds), gets to roof stage having spent 17, sees a building standing there, and reasonably concludes he has 23 million to finish 71 percent of the work. He doesn’t. He needs 42. The shortfall was locked in before the first block went down, in the decision to price the structure and guess at the rest.
You can disagree with me on this and plenty of people do. The common view is that stalled houses are a money problem. I think they’re a sequencing problem that only shows up as a money problem. Same house, same budget, different order of decisions, and it gets finished.
The line items that surprise people
The 28 doors came to GYD 3,327,000. The entire roof, framing and zinc and labour, came to GYD 3,239,904. The doors cost more than the roof.
The electrical package at GYD 5,165,100 is 1.6 times the roof. It’s 125A panel, roughly 3,990 linear feet of cable, 114 receptacles, 21 switches, 81 LED fixtures and nine dedicated AC circuits. None of it is visible when it’s done.
The kitchen cabinetry and countertop alone, at GYD 3,200,000, is another roof.
On the ceramic tile, material was GYD 410 per square foot and installation was GYD 2,000. The labour is nearly five times the tile. Anybody who has priced a house by walking through Gafoors adding up materials has already got it badly wrong.
Windows tell the same story. Twenty-six aluminum casements cost GYD 560,557 to buy and GYD 700,000 to install. Fitting them costs more than the windows.
And septic plus water storage together are GYD 3,717,920, 6.3 percent of the build. Two tanks, platform, booster pump, underground piping, a reinforced concrete septic tank and a soakaway field. It’s the money nobody budgets, because when it’s finished you can’t see any of it.
What finishing actually costs
Everything from the plumbing rough-in forward, so plumbing, electrical, AC, floors, paint, kitchen, bathrooms, closets, stairs, trim, water and septic, comes to GYD 41,624,506. That’s 71 percent of the build.
Break out the finishing package on its own, the GYD 9,270,934 line, and it’s kitchen cabinetry and countertop at 3.2 million, the four-appliance package at 587,400, the three ensuites and powder room fully tiled and waterproofed with shower and vanity at 1,890,000, five closets and a fifteen-step staircase with handrail at 1,159,500, and 838 linear feet of baseboard with 812 feet of casing at 598,878.
That single line is 15.8 percent of the whole house. More than the foundation.
Here’s how I run it, and it’s the opposite of how most people do it. I price the kitchen and the bathrooms before I price the footings. Not after. If the finishing package doesn’t fit the budget, the answer is a smaller house, not cheaper finishes. I’d rather take 300 square feet out of a design than put melamine where the client wanted stone, because the square footage is a decision you make once and the finishes are a decision you regret every day for twenty years.
Foundation, and why coastal soil moves the number
The foundation and ground structure came in at GYD 8,313,544, the second-largest line in the build.
That’s 242 linear feet of reinforced strip footing at 24 by 8 inches, twenty 10 by 10 reinforced concrete columns, 8-inch CMU stem walls, and a 1,458 sq ft ground slab on 12 inches of compacted sand fill with BRC mesh and a vapour barrier.
On a Golden Grove lot that sequence works. Move the same house to ground that needs piling and the foundation number moves hard, and it moves before you’ve built anything you can see.
Footprint drives it too, which is why single-storey versus two-storey changes the total. This is the single biggest reason a per-square-foot rate from one project doesn’t transfer cleanly to another. If your house is big enough to need a soil test, get it before you commit to a design, not after.
Why the documented total is lower than our current rate
The estimate above works out to GYD 20,574 per square foot. Standard spec today is 28,000 to 32,000. I’d rather explain the gap than have you do the arithmetic and wonder what I’m hiding.
That job was one of our first in Guyana and it was priced accordingly. Early work carries early pricing. The same house, same drawings, same specification, priced today lands between GYD 80 and 91 million.
Specification moves the number as much as timing does. Standard spec means prepainted zinc rather than concrete tile, SPC click-lock through the living areas rather than imported hardwood, melamine and MDF cabinetry rather than solid wood, aluminum casements rather than impact glass. Move to a custom layout with better roofing and stronger detailing and you’re at 33,000 to 42,000. Imported materials, complex elevations and full-time supervision put you at 45,000 to 55,000 and up.
The exclusions matter just as much, and they aren’t small: no land, no drawings, no permits, no fill, no fence, no driveway, no solar, no generator, no VAT.
What doesn’t change with the rate is the shape of the spending. Whether this house costs 59 million or 91 million, the roof still goes on at 29 percent and the finishing still eats 71. That’s the part worth taking away.
Drawings, permits and professional fees
In most cases these sit outside the build cost. You pay an architect, then a structural engineer, then the permit fees, and only then do you go looking for a contractor to price what somebody else drew.
CH&PA processing fees run GYD 36,000 to 109,000, with site inspection fees in the same band again. Architectural drawings and structural calculations are separate and depend on the complexity of the design. A soil test, where the house needs one, costs GYD 1.3 million for one hole and about 2.4 million for two. The detail is in soil test cost in Guyana.
We do it differently, and it is worth saying plainly because it changes the arithmetic above. We are a design and build firm, so the architectural, structural and working drawings, your finish selections, the CH&PA submission and its fees all sit inside the rate quoted here. That is normally 3 to 5 percent of construction cost and it does not arrive as a separate bill.
For a house over three storeys, or a subdivision, you’re dealing with CH&PA directly. Up to three storeys inside a municipality it’s the Mayor and City Council, and outside a municipality it’s the NDC. CH&PA’s Single Window system at chpa.gov.gy lets you file without flying in, which matters if you’re managing from Brampton or Brooklyn.
What the government covers, and what it doesn’t
The Steel and Cement Housing Subsidy provides one sling of cement plus the steel for the foundation on homes estimated at GYD 6 million and under, and two slings of cement on homes valued between GYD 6 million and GYD 25 million. Over 2,000 vouchers and more than GYD 500 million have been distributed since the programme opened in 2022.
Budget 2026 allocated GYD 7.5 billion to a housing improvement subsidy, and removed VAT from locally manufactured furniture including doors and moulding, which takes some pressure off the finishing stage.
Useful. Now look at the table again. The foundation on this house was GYD 8.3 million. A sling of cement and the foundation steel is real help at the bottom of the market and it is not a plan for a 2,852 sq ft two-storey.
What the bank approves and what the project costs
A bank approves against an appraised value. A build costs what the build costs. Those are two different numbers and the gap between them is where most projects come apart.
If the approval is 40 million and the finished project is 59 plus contingency, you don’t have a financing problem at month one. You have one at month nine, when the structure is up, the disbursements have run through, and the finishing package that represents 71 percent of the work hasn’t started.
Building from overseas: the lines nobody budgets
Independent supervision is the one to plan for. If your only eyes on site belong to the person you’re paying, you don’t have oversight, you have a report.
Cameras on the site from the day the foundation goes in, with cellular data if the power isn’t reliable. If you’re shipping a container of tiles or fixtures, you’re paying customs duty, a clearing agent and delivery from the port, and materials can sit for weeks if the paperwork is off. Order well ahead of when the trade needs them.
The cost that never appears on any estimate is decision lag. A choice that takes an hour in Georgetown takes four days across a time zone, and on a site with a crew waiting, four days is money.
Five things that push a Guyana build over budget
Pricing the structure and estimating the finishes. That’s the big one, and the table above explains why.
Skipping the soil test on a house big enough to need one, then discovering the foundation needs more than you allowed for once you’re already committed to the design.
Changing the scope mid-build. Every change order after the walls are up costs more than the same decision made on paper.
Buying material by walking the aisles instead of working from measured quantities. The tile numbers show what that does.
Building to the limit of the approval with no contingency. We build in 10 percent. On this house that’s GYD 5.87 million, and on most projects it gets used.
Frequently asked questions
A standard-spec two-storey runs GYD 28,000 to 32,000 per square foot for construction. On a 2,852 sq ft four-bedroom that’s roughly GYD 80 to 91 million. The drawings, the permit submission and the permit fees are inside that figure. Land and yard works are separate.
GYD 28,000 to 32,000 at standard specification, 33,000 to 42,000 for custom mid-range, and 45,000 to 55,000 and up for high-end with imported materials. The documented estimate in this article prices below all of these because it was an early project, and it’s published for the phase proportions rather than the total.
About 29 percent. Foundation, upper floor structure, roof and exterior walls came to GYD 17 million of a GYD 58.7 million build. A roofed house has not spent a third of its budget.
On this build, the kitchen, bathrooms, closets, stairs and trim package at GYD 9.27 million, 15.8 percent of the total. The foundation was second at 14.2 percent. The roof was 5.5 percent.
No. Nor yard sand fill, driveway, fence, solar, generator, or VAT. The drawings and permit fees are included.
Ten percent minimum. On this project that’s GYD 5.87 million.
One sling of cement and foundation steel for homes valued at GYD 6 million and under, two slings of cement for homes between GYD 6 million and GYD 25 million, applied for through CH&PA.
Because the structure is priced accurately and the finishes are guessed at. The money runs out where the spending accelerates, which is after the part you can see is finished.
What your own number is
Everything above is one project on one lot. Your fill requirement, your footprint, your finish selections and your available capital produce a different number, and no table on the internet can give it to you.
That is what a Build-Readiness Review is for. A real quantity takeoff on your drawings, priced against current supplier rates, then tested against what you actually have to spend. At the end you know whether your budget finishes the house. Some people take that document and walk, which is a far better outcome than finding out in year two.
US$1,500, credited in full against your build. Application required, and we decline more projects than we take.
Four questions. About a minute. Free.
UNDER US$500,000?
That’s the range we built Pristine Ridge Homes for. Four fixed-price homes from GYD 33M to 72M (about US$165,000 to 360,000), drawings and permits included, built on your land. See which one fits →
Sources
Cost figures are drawn from a BackHome Developments project estimate dated May 2026 for a 2,852 sq ft two-storey on a Golden Grove, East Bank Demerara lot, with client details removed. It was an early project and the total reflects early pricing; standard-spec construction today runs GYD 28,000 to 32,000 per square foot. Material pricing confirmed against Gafoors, GuyanaFrame and Floor It Guyana. Labour rates reflect completed projects. Exchange rate 1 USD to 200 GYD. Figures exclude VAT.
Permit fees and programme details from the Central Housing and Planning Authority (chpa.gov.gy) and the Ministry of Finance Budget 2026.
This is a documented estimate for one project, not a quotation. Every site, design and specification prices differently.