Last verified: August 2026
Finishing a house that stopped at roof stage costs about 71 percent of a full build. On a 2,852 sq ft two-storey at standard spec, that’s GYD 57 to 65 million of work still to do, on a structure that already looks nearly complete from the road.
That’s the number nobody tells people who own a stalled house. They look at the block and the zinc and assume the hard part is behind them. The spending hasn’t started.
Haven’t started yet? Run your budget through the Completion Check before the first block goes down. It shows the phase where your money stops, so you never end up owning a house like this.
Why a roofed house has spent so little
We published the full phase-by-phase costing on a standard-spec two-storey, and the numbers are worth repeating here.
Foundation and ground structure took 14.2 percent of the budget. Upper floor structure 4.4 percent. Roof framing and zinc 5.5 percent. Exterior walls 5 percent. Add them up. Block up, roof on, and you’ve spent 29.1 percent.
The remaining 70.9 percent is interior partitions, windows, doors, plumbing, electrical, air conditioning, floor finishes, painting, kitchen, bathrooms, closets, stairs, trim, water storage and septic. All of it is work you can’t see from the road and all of it costs more than the shell.
On the documented project that remaining work came to GYD 41,624,506. Priced at today’s standard-spec rate of 28,000 to 32,000 per square foot, the same remaining scope on the same house is GYD 57 to 65 million.
Where the remaining money sits
| Phase still outstanding | Share of full build |
|---|---|
| Kitchen, bathrooms, closets, stairs, trim | 15.8% |
| Electrical | 8.8% |
| Floor finishes | 7.3% |
| Interior partition walls | 6.7% |
| Painting, interior and exterior | 6.7% |
| Plumbing | 6.1% |
| Doors | 5.7% |
| Air conditioning | 5.4% |
| Water storage and pressure system | 3.3% |
| Septic and wastewater | 3.1% |
| Windows | 2.1% |
| Total remaining | 70.9% |
Look at the top line. The kitchen, bathrooms, closets, staircase and trim package is 15.8 percent of the whole house, more than the foundation and more than double the roof. That’s the single item people leave out of their finishing estimate, because it’s the part they think of as decoration.
Electrical is next at 8.8 percent. A 125A panel, roughly 3,990 linear feet of cable, 114 receptacles, 21 switches, 81 fixtures and nine dedicated AC circuits. Invisible when it’s done, and 1.6 times the cost of the roof.
What makes finishing cost more than the same work would have cost new
Everything above assumes the remaining scope prices like new work. On a stalled house it usually doesn’t, for four reasons.
Your old budget is dead. A house that stopped in 2023 was budgeted at 2023 rates. Labour has moved since, materials have moved, and the oil economy has pulled skilled trades toward projects that pay better. The remaining 71 percent has to be repriced at today’s numbers, not adjusted from the old ones.
The structure has been sitting. Exposed rebar rusts. Timber joists left open to weather move and split. Blockwork that never got rendered has been absorbing water through every rainy season since it stopped. Some of that is cosmetic and some of it is structural, and you cannot tell which from photographs.
Nobody inherits another builder’s sequencing for free. Anyone quoting your unfinished house has to work out what’s actually there, what was done properly and what has to come out. That assessment costs money before a single price is quoted, and any builder who skips it and quotes off the drawings is guessing.
The finishing trades are labour-dominated. On the documented project, ceramic tile cost GYD 410 per square foot for material and GYD 2,000 per square foot to lay. Window installation cost GYD 700,000 against GYD 560,557 for the 26 windows themselves. Fitting them cost more than buying them. The remaining 71 percent isn’t a shopping list, it’s mostly people’s time, and people’s time is what’s gone up.
The harder question
Most owners of stalled houses ask what it costs to finish. The better question is whether to finish the house that’s standing there.
Two things are usually true at once. The structure is sound and worth completing. And the design it was built to is no longer a design the owner can afford, because it was drawn when the budget looked different.
Trying to complete the original drawings is the second-biggest mistake I see, right after underpricing the finishes in the first place. Four ensuites made sense on paper in 2022. Finish two properly, rough in the others and close them off, and the house gets occupied. A house you live in is worth more than a house that’s 80 percent of somebody’s earlier ambition.
And sometimes the honest answer is to sell the structure. If the remaining work is 60 million and the finished house appraises at 75 in that location, you’re spending 60 to make 15. Nobody wants to hear that from a builder. It’s still true, and you should hear it before you commit, not after.
What to do before you get a price
Get the structure assessed by someone who isn’t quoting the work. Foundation, columns, beams, exposed steel, roof timbers, blockwork. Written, with photographs.
Reprice the remaining scope at current rates rather than escalating the old budget. Those are different exercises and they produce different numbers.
Decide the finished specification before anyone quotes, because the difference between standard and high-end finishing on the remaining 71 percent is tens of millions.
Confirm what’s actually installed underground. Septic and water storage are 6.4 percent of a build and they’re easy to assume were done because you can’t see whether they were.
Then carry a contingency. Ten percent on new work. On a stalled house I’d want more, because the assessment tells you what’s visible and the first month of work tells you the rest.
Frequently asked questions
About 71 percent of a full build if the house stopped at roof stage. On a 2,852 sq ft two-storey at standard spec that’s GYD 57 to 65 million, before any remedial work.
About 29 percent by cost. Foundation, upper floor structure, roof and exterior walls together account for 29.1 percent of a standard-spec build.
Usually, because the shell is done. But the saving is smaller than people expect, since the shell is under a third of the cost, and remedial work on a structure that has sat exposed can eat into it.
Banks assess a partially built structure differently from a vacant lot, and the appraisal drives what they’ll lend. Speak to the lender before you commission a full set of quotes.
The kitchen, bathrooms, closets, staircase and trim package, at 15.8 percent of the full build cost.
You don’t, from looking. Have it assessed in writing by someone with no interest in quoting the completion work.
What your own number is
Everything above is one project on one lot. Your fill requirement, your footprint, your finish selections and your available capital produce a different number, and no table on the internet can give it to you.
That is what a Build-Readiness Review is for. A real quantity takeoff on your drawings, priced against current supplier rates, then tested against what you actually have to spend. At the end you know whether your budget finishes the house. Some people take that document and walk, which is a far better outcome than finding out in year two.
US$1,500, credited in full against your build. Application required, and we decline more projects than we take.
Four questions. About a minute. Free.
Sources
Phase percentages are drawn from a BackHome Developments project estimate for a 2,852 sq ft standard-spec two-storey on a Golden Grove, East Bank Demerara lot, with client details removed. Material pricing confirmed against Gafoors, GuyanaFrame and Floor It Guyana. Current-rate figures use standard-spec construction at GYD 28,000 to 32,000 per square foot. Drawings and permits are included in the rate. Figures exclude land, yard works and VAT.
Every stalled structure is different and none of the above replaces a site assessment.