A fixed price is only worth what the scope behind it is worth. A number on one page with no measured quantities, no named exclusions and no expiry isn’t a fixed price. It’s a starting position, and every clarification after that becomes a variation you pay for.
Most homeowners in Guyana ask whether the price is fixed. Almost nobody asks what it’s fixed to. That’s the question.
The number is the last page, not the document
A properly built estimate for a house runs to fifteen or so sections, each broken to line items, each line carrying a quantity and a source.
Not “foundation.” Instead: 242 linear feet of reinforced strip footing at 24 by 8 inches with half-inch rebar at 16 inches on centre, excavation and blinding included. Twenty reinforced concrete columns at 10 by 10, four half-inch vertical bars, three-eighths ties at 8 inches on centre. A 1,458 square foot ground slab, four inches of concrete over twelve inches of compacted sand fill, BRC mesh and a vapour barrier.
That level of detail isn’t there to look impressive. It’s there because every one of those numbers can be checked against the drawings, and because a contractor who has counted 242 feet of footing has actually taken off the job. One who writes “foundation” has not. You can see what that looks like across a whole house in our measured line items.
If the document you’re holding can’t be checked line by line against your drawings, the price isn’t fixed. Nobody has established what it covers.
Quantities have to come from named drawing sheets
An estimate should say where its numbers came from. Architectural sheets for the room areas and openings. Structural sheets for the framing, roof and connections.
That matters because it makes the estimate falsifiable. If your architect revises a sheet, you know immediately which line items move. If a builder quotes without referencing your drawings, he’s pricing a house shaped like the last one he built.
The 26 windows and 28 doors on a build come off a schedule, not an impression. Sixteen casements at one size, six at another, four at a third. The 28 doors split across a front entry, fifteen typical interiors, five bi-folds, five specialty, a patio slider and a garage door. Each with hardware. That’s a countable list, and the count is what makes the price hold.
Materials should be traceable to suppliers
Line items should name where the pricing came from. Gafoors for cement, block, rebar, zinc, sanitary and the mini-split units. GuyanaFrame for light-gauge steel studs and track. Floor It for the SPC and the trim profiles.
Where a rate reflects work already completed rather than a supplier quote, the document should say so. Roof carpentry and zinc laying at a confirmed rate from finished jobs is a different kind of number from a materials price off a shelf, and you’re entitled to know which you’re looking at.
Anonymous pricing is where padding lives. If nobody can tell you which supplier a figure came from, nobody can tell you whether it moved.
Exclusions are the most important page
Every fixed price excludes something. The honest ones say what.
On a standard-spec two-storey the exclusions were yard sand fill, driveway, perimeter fence, solar system and standby generator, and the figures were stated exclusive of VAT.
Look at what those exclusions are worth. Fencing on a 50 by 100 lot runs GYD 6 to 10.5 million. Driveway, bridge and landscaping run 2 to 5 million. Sand fill to three feet is 500,000 to 600,000. A five kilowatt solar installation benchmarks around 1.5 million. That’s potentially 17 million sitting outside a “fixed price” and it’s entirely legitimate, provided it’s written down.
A contract with no exclusions clause is not more generous than one with a long list. It’s a contract where the argument hasn’t happened yet.
I’d rather have an honest estimate with a wide range and a full exclusions list than a confident single number with nothing named. The first one tells you where you stand. The second tells you what someone wanted you to hear.
The exchange rate and the expiry date
An estimate should state the exchange rate it used. At 1 USD to 200 GYD, a large share of a build is imported, priced in USD and converted. If the rate isn’t stated you can’t tell whether a later increase is a genuine cost movement or a renegotiation.
It should also expire. Thirty days is normal. A quote that stays valid indefinitely sounds like a favour and isn’t one, because material pricing in Guyana moves and any builder who fixes a number beyond a sensible window has either padded it heavily or hasn’t thought it through. The expiry protects you as much as it protects him.
Contingency belongs outside the price, stated
Ten percent contingency on a 58.7 million build is 5.87 million. That should appear as its own line, under the total, described as a reserve.
Folding it into the price hides it. Leaving it out entirely pretends construction is predictable. Neither serves you. State it, keep it, and if you don’t use it you keep it.
What a fixed price cannot fix
It cannot fix ground conditions you haven’t tested. Piling on an 1,800 square foot two-storey runs 9 to 13 million where the soil calls for it, and no honest builder fixes that number before the ground is tested.
It cannot fix scope you change. Every change order after the walls are up costs more than the same decision made on paper, and a fixed price that survives changes is a fixed price that was never tight.
It cannot fix what your drawings don’t show. If the drawings don’t specify a finish, the estimate carries an allowance, and an allowance is not a fixed price. It’s a placeholder with your name on the difference.
What to ask before you sign
Ask which drawing sheets the quantities came from. Ask which suppliers the material rates came from. Ask what’s excluded and get it in writing. Ask what exchange rate was used. Ask how long the price holds. Ask which items are allowances rather than fixed. Ask what the contingency is and who holds it.
Seven questions. A builder who has done the work answers all seven in a few minutes. One who hasn’t will tell you the price is fixed and change the subject, and that’s the answer you needed.
Frequently asked questions
Line-item scope with measured quantities, the drawing sheets those quantities came from, named material suppliers, a written exclusions list, the exchange rate used, a validity period, and a separately stated contingency.
Only if the scope is defined. A fixed price with no measured quantities and no exclusions list carries more risk than a detailed estimate with an honest range.
Commonly yard sand fill, driveway, perimeter fence, solar and standby generator, and VAT. Those exclusions can total well over 15 million on a standard lot.
Around thirty days. Material pricing moves, and a quote with no expiry has either been padded or hasn’t been properly costed.
No. It should sit below the total as a stated reserve, typically 10 percent, so you can see it and control it.
The estimate will carry an allowance for it, and allowances aren’t fixed. Specify finishes before pricing if you want the number to hold.
What your own number is
Everything above is one project on one lot. Your fill requirement, your footprint, your finish selections and your available capital produce a different number, and no table on the internet can give it to you.
That is what a Build-Readiness Review is for. A real quantity takeoff on your drawings, priced against current supplier rates, then tested against what you actually have to spend. At the end you know whether your budget finishes the house. Some people take that document and walk, which is a far better outcome than finding out in year two.
US$1,500, credited in full against your build. Application required, and we decline more projects than we take.
Four questions. About a minute. Free.
Sources
Contract structure and examples are drawn from a BackHome Developments project estimate for a 2,852 sq ft standard-spec two-storey on a Golden Grove, East Bank Demerara lot, with client details removed. Material pricing referenced against Gafoors, GuyanaFrame and Floor It Guyana. Exchange rate 1 USD to 200 GYD.
Site works ranges are drawn from BackHome purchasing on East Bank projects. Solar benchmark from published local guidance.