The money is the one part of the build you can’t see from Toronto.
You can see photos. You can hear that the walls are up. What you can’t see is whether the US$40,000 you sent last month went into your walls, or into somebody else’s roof down the road.
Most houses that stop in Guyana don’t stop because the builder vanished. They stop because the money went out faster than the work came in, and by the time anyone noticed, there wasn’t enough left to finish.
The short answer
Pay a builder in Guyana by stage, after the stage is done and you’ve seen it, into a company account, in the currency the contract is written in. Never pay ahead of the work, and never send cash home with a relative. Ask for a statement after every payment showing what you’ve paid, what’s been built and what’s left.
Pay for work you can see
A payment stage should be something a person can stand in front of and check. Foundation poured. Walls up to the ring beam. Roof on. Pipes and wires in the walls. Not “month three.”
Paying by the month pays for time. Paying by the stage pays for house. Only one of those gets you closer to moving in.
Here’s the number to keep in your head. On our documented Golden Grove estimate, a house is only about 29 percent of its cost done when the roof goes on. If a builder has had half your money and you’re looking at a roof, the other half of the house is coming out of money you don’t have yet.
| What you pay for | What you should be able to check before you pay |
|---|---|
| Design and drawings | Drawings, a written specification and a costed schedule in your hands |
| Foundation | Footings and slab poured, with photos of the steel before the concrete covered it |
| Walls | Block walls and ring beam complete, openings where the drawings put them |
| Roof | Roof on and closed in |
| Rough-ins | Pipes and wires in the walls before they’re plastered over |
| Finishes | Kitchen, bathrooms, floors, doors and paint installed |
| Handover | A final walkthrough, with every item on the list fixed |
The deposit tells you everything
Ask a builder how he wants to be paid before you ask him anything else. The answer tells you how his business runs.
A big deposit before anything is drawn or priced means one of two things. He needs your money to finish somebody else’s job, or he’s buying materials for a house nobody has costed. Neither one is your problem until you pay it. Then it’s all yours.
Your first money should buy paper you can hold: drawings, a specification and a costed schedule. Paper you can carry to another builder if this one disappears.
Where the money goes, and in what currency
Pay the company named on the contract, into its business account. Not his personal account, and not his cousin’s. If the name on the account doesn’t match the name on the contract, stop and ask why.
Then the currency. Your contract is probably in Guyana dollars, and your money is in US dollars, Canadian dollars or pounds. The Guyana dollar has been steady against the US dollar for years, sitting between about 198 and 213 since 2008, and around 208 in October 2026. Steady isn’t fixed, though, so agree in writing whose problem the difference is.
If the contract is in Guyana dollars, send so the Guyana-dollar amount on the invoice is the amount that lands. A transfer service like Wise can deliver a set Guyana-dollar amount into a Guyanese bank account, and a bank wire does the same job. Compare the total cost on the amount you’re actually sending. On a stage payment of GYD 10 million, two percent is GYD 200,000 gone to fees and rates.
On a job I invoiced this month, for clients paying from the UK, every invoice shows the Guyana-dollar figure that has to land, and the transfer is set to deliver exactly that. Any difference from the rate gets settled on the final payment. It’s written into the invoice, so nobody argues about it at the end.
If a bank is lending you the money
Banks in Guyana release construction loans in stages, after someone inspects the work already standing. They won’t pay ahead of the building, which protects you as much as them. I covered how that works in building with a mortgage.
The catch is time. If every stage waits a week for the inspector, that’s more than a month gone across the build. Ask your bank whether inspections can be booked ahead of the stage finishing, not requested after it. And your own money, the part the loan doesn’t cover, should follow the same stages. Don’t spend it first and hope the bank catches up.
What you should get after every payment
A receipt is the minimum. What you want is a statement: what you’ve paid so far, what’s been built for it, and what’s left to pay. If the three numbers don’t line up, you find out after one payment, not after six.
On our builds it sits in the client portal. Every payment request arrives with that statement, next to the week’s site logs and photos. You see the work before you pay for it, from wherever you live.
Red flags
- Half the money up front, or a “materials deposit” before anything is costed.
- “Send it now before steel goes up.”
- Payments by the month, not by the stage.
- A personal account, or a different name on the account than on the contract.
- No receipts, or receipts on WhatsApp only.
- Photos you can’t date, of work you can’t tie to your lot.
Any one of these is a conversation. Two of them is a reason to walk away.
The rule behind it
I build by what I call the Completion Doctrine. A house doesn’t start until it’s designed and costed to the last fixture, and the money to finish it exists in writing, before a single block is laid. Starting is easy. Finishing is rare.
Staged payments are how that rule holds once the build begins. The money for every stage exists before the first stage starts, and none of it leaves your hands until the stage it pays for is standing.
Frequently asked questions
How should I pay a builder in Guyana if I live abroad?
By stage, after the stage is finished and you’ve seen it, into the company’s business account, in the contract currency, with a statement after each payment.
How much deposit should a builder in Guyana ask for?
Enough to pay for real work you can hold: drawings, a specification and a costed schedule. Be wary of a large share of the build paid before anything is drawn, priced or permitted.
What is the exchange rate risk on a Guyana build?
Small but real. The Guyana dollar has stayed between about 198 and 213 to the US dollar since 2008. Agree in writing which currency the contract is in and who carries the difference.
Do Guyanese banks release construction loans in stages?
Yes. The money is released against completed stages after an inspection. Ask how long inspections take and whether they can be booked in advance.
Who this is for
If you’re planning a custom house from abroad and want the money mapped stage by stage before anyone breaks ground, apply for a Build-Readiness Review. We take your budget, your land and the house you have in mind, and cost it before anyone draws a line. If you go ahead and build with us, the fee comes off the build in full.
Not ready yet? Get the BackHome Building Guide. It’s the ten pages I’d want you to read before you hire anyone.
US$1,500. Application required, and we decline more projects than we take.
Sources
Cost at roof-on comes from a BackHome Developments estimate for a 2,852 sq ft standard-spec two-storey at Golden Grove, East Bank Demerara, with client details removed. Exchange rates are from Trading Economics (USD/GYD, 2008 to October 2026). Transfer details are from Wise’s Send money to Guyana page, October 2026.
This is a planning guide, not financial advice.