Last verified: September 2026
Forty million Guyana dollars buys a finished standard-spec house of about 1,250 to 1,430 square feet. Three bedrooms if the layout is efficient. Not four, and not two storeys. Drawings and permits are included in the rate. Land and yard works are not.
Most people arrive at 40 million from the other direction. They have a design of 2,000 square feet or more, they get an approval or they have savings around that figure, and they assume it fits. It doesn’t, and the way it fails is specific enough to map out.
Your number isn’t 40 million? Put your own budget in the Completion Check. Four questions, and it shows what your money finishes and where it stops.
The arithmetic
Standard-spec construction in Guyana runs GYD 28,000 to 32,000 per square foot. That covers everything from footings to paint: foundation, floor structure, roof, walls, windows, doors, plumbing, electrical, air conditioning, floor finishes, painting, kitchen, bathrooms, closets, stairs, trim, water storage and septic.
Divide 40 million by those rates. At 28,000 per square foot, 40 million builds 1,428 square feet. At 32,000, it builds 1,250.
So a compact three-bedroom single-storey, finished, with a working kitchen and bathrooms and water and septic. That’s a real house and plenty of families are happy in one. It is not the house most people picture when they say forty million.
What happens when you put 40 million against a 2,000 sq ft design
This is where it gets useful, because this is what people actually do.
A 2,000 square foot house at 28,000 per square foot costs 56 million. Your 40 million is 71 percent of that.
Now look at where 71 percent of the money takes you, using the phase-by-phase breakdown from a documented standard-spec build.
| Phase | Share | Running total |
|---|---|---|
| Foundation and ground structure | 14.2% | 14.2% |
| Upper floor structure | 4.4% | 18.6% |
| Roof framing and zinc | 5.5% | 24.1% |
| Exterior walls | 5.0% | 29.1% |
| Interior partition walls | 6.7% | 35.8% |
| Windows | 2.1% | 37.9% |
| Doors | 5.7% | 43.6% |
| Plumbing | 6.1% | 49.7% |
| Electrical | 8.8% | 58.5% |
| Air conditioning | 5.4% | 63.9% |
| Floor finishes | 7.3% | 71.2% — your money runs out here |
| Painting | 6.7% | 77.9% |
| Kitchen, bathrooms, closets, stairs, trim | 15.8% | 93.7% |
| Water storage and pressure system | 3.3% | 97.0% |
| Septic and wastewater | 3.1% | 100% |
Your money runs out at 71.2 percent. Right at the end of floor finishes.
Read what’s on the other side of that line. No painting, inside or out. No kitchen. No bathroom fittings, no tiled showers, no vanities. No closets, no staircase handrail, no baseboard or casing. No water tanks, no pressure pump. No septic tank and no soakaway.
You have a structure with tiles on the floor and no way to wash in it. That’s the house you drive past every day on the East Bank with the zinc on and nobody living in it.
The owner didn’t get cheated. He built a 56 million house with 40 million.
Why the shortfall shows up so late
Everything expensive is at the back.
By the time the roof is on you’ve spent 29.1 percent. The house looks substantially built. Family drives past and congratulates you. That impression is the trap, because 71 percent of the money is still ahead of you and none of it produces a visible change as dramatic as a roof going on.
The single largest item in a build is the kitchen, bathrooms, closets, stairs and trim package, at 15.8 percent. It’s larger than the foundation. It’s nearly three times the roof. And it’s the last thing you pay for, which means it’s the first thing to get sacrificed when the money is tight.
Septic and water storage together are 6.4 percent. Those two decide whether anyone can live in the house at all, and they sit at the very bottom of the spending order.
What 40 million doesn’t cover at any size
The rates above are construction only. Outside them sits the land, the drawings and structural calculations, the permits, a soil test if the house needs one, and the yard works.
On the East Bank corridor, published market figures put Providence and Herstelling around GYD 15 to 30 million and Diamond and Grove around 12 to 25 million. A CH&PA allocation is far cheaper, with lots starting near GYD 100,000 for low-income applicants and middle-income lots generally between 500,000 and 1.5 million.
Site works on a fresh 50 by 100 lot run 8.5 to 16.1 million: sand fill at 500,000 to 600,000, fencing at 6 to 10.5 million, driveway and bridge and landscaping at 2 to 5 million. A single-storey of about 1,300 square feet on ordinary ground won’t usually need a soil test or piling. Where a bigger house does, the test is 1.3 million a hole, and piling on an 1,800 square foot two-storey runs 9 to 13 million.
CH&PA processing runs GYD 36,000 to 109,000, with site inspection fees in the same band again. A 5kW grid-tied solar installation benchmarks around GYD 1.5 million locally. And VAT is excluded from construction figures unless someone tells you otherwise.
Add land at the low end of the East Bank range and you’re at 60 million or more before the house is finished. Forty million was never the project budget. It was the construction line.
What I’d tell you to do with 40 million
Build 1,300 square feet and finish it.
That’s the whole recommendation and most people don’t like it. The instinct is to build the 2,000 square foot shell now and finish it later when money comes. I’ve watched enough of those to say plainly that later is more expensive than now. A structure that sits through two rainy seasons unrendered and unpainted costs money to bring back before it costs money to finish, and the rate you’ll pay for the remaining work in three years is not the rate you’d pay today.
There’s a second version of the same mistake, which is keeping the 2,000 square feet and cutting the specification to fit. Cheaper fittings, thinner tile, skip the AC rough-ins. You end up with a large house full of things you’ll replace, and the square footage you bought at the expense of the finishes is the one decision you can never revisit.
Square footage is permanent. Finishes are permanent in practice, because nobody rips out a kitchen they just paid for. Pick the number of square feet your money finishes properly, and build that.
Frequently asked questions
About 1,250 to 1,430 square feet at standard specification, finished. That’s construction only, excluding land and yard works.
Not a finished one at any usable size. A 2,000 sq ft two-storey at standard spec runs around 56 million, and 40 million takes you to roughly the floor-finishes stage with no kitchen, bathrooms, water or septic.
On a 2,000 sq ft design it covers about 71 percent of the work: structure, partitions, windows, doors, plumbing, electrical, air conditioning and floor finishes. It stops before painting, kitchen, bathrooms, water storage and septic.
On the East Bank corridor, generally no. Published land ranges for Providence and Herstelling sit around 15 to 30 million. A CH&PA allocation changes that arithmetic considerably.
The kitchen, bathrooms, closets, staircase and trim package, at 15.8 percent of construction cost. More than the foundation.
It costs more than finishing a smaller house now. The structure deteriorates while it waits and the remaining work reprices at future rates.
What your own number is
Everything above is one project on one lot. Your fill requirement, your footprint, your finish selections and your available capital produce a different number, and no table on the internet can give it to you.
That is what a Build-Readiness Review is for. A real quantity takeoff on your drawings, priced against current supplier rates, then tested against what you actually have to spend. At the end you know whether your budget finishes the house. Some people take that document and walk, which is a far better outcome than finding out in year two.
US$1,500, credited in full against your build. Application required, and we decline more projects than we take.
Four questions. About a minute. Free.
Sources
Phase percentages are drawn from a BackHome Developments project estimate for a 2,852 sq ft standard-spec two-storey on a Golden Grove, East Bank Demerara lot, with client details removed. Construction rates of GYD 28,000 to 32,000 per square foot reflect standard specification in 2026. Site works ranges are drawn from BackHome purchasing on East Bank projects.
Land price ranges, CH&PA lot pricing, permit and inspection fees and solar installation figures are drawn from published local guides and CH&PA (chpa.gov.gy). Soil test pricing is from a geotechnical engineering firm in Guyana, September 2026. Verify current figures before budgeting.
This is a planning guide, not a quotation. Every site and design prices differently.